Construction of the Kamuzu Central Hospital One Stop Center building in Lilongwe began in August 2015 and was scheduled to be finished by December 2015. In October, the walls were up and seemed to be in progress and on schedule.

Unfortunately construction stopped in late 2015 and therefore the building could not be finished as scheduled. The contractors resumed construction in late January and we were informed that it will be finished by end February 2016.

On 9th February 2016, FOL visited the site to check the progress but there were no builders around, it seemed to be on hold once again. The building is however roofed and awaiting other finishing materials. It is doubtful that it will be completed on schedule (end February). We hope the building will be completed in the first quarter of the year so that the OSC can be launched and victims can begin to access OSC services effectively.  

Recent Posts

16 Days of Activism Public Debate - Radio Panel Broadcast

UN Women and Ministry of Gender, Children, Disability and Social Welfare…

CONGOMA NGO Week 2015

FOL participated in the CONGOMA NGO Week for the first time.

KCH (Lilongwe) OSC Building in Progress!!!!!

Progress report on the KCH (Lilongwe) OSC Building

UNICEF partners with Fountain of Life!!!

Small Scale Funding Agreement (SSFA) Between UNICEF and FOL

Construction of Kamuzu Central Hospital One Stop Center BEGINS!

Construction has began on the much anticipated One Stop Center at Kamuzu…